HT Panel PPM Maintenance
Procedure and checkpoints of maintenance activity.


Contents
  1. HT panel PPM Maintenance.
  2. HT panel PPM checklist template.
  3. HT panel PPM annualy schedule.
  4. HT panel PPM Maintenance procedure.

1 -HT panel PPM Maintenance :

HT panel preventive maintenance: schematic diagram and checklist.

2 -HT Panel maintenance checklist template.:

HT panel preventive maintenance: template of checklist.

3 -HT Panel PPM Maintenance annualy schedule:

In one year maintenance activity is carried out many times according time schedule so it is called maintenance frequency which is below mentioned.

  • Monthly PPM
  • Quarterly PPM
  • Half yearly PPM
  • Yearly PPM

4 -HT panel PPM maintenance activity procedure:

PPM working procedure is carried out according time schedule. The procedure of PPM is going to explain according time schedule as per below mentioned.

1 - Monthly Preventive maintenance:

When once im a month the PM activity is carried out then it is called as monthly PM activity. A maintenance checkpoint list is followed during maintenance activity which is given below mentioned.

  • Clean the panel with air blower and clothes.
  • Check all busbar connection input and output.
  • Check all circuit breaker input and output connections.
  • Check any abnormal sound in panel.
  • Check earthing connection with panel.
  • Check all measuring instruments meters.
  • Check all circuit breaker functions
  • Check indicators, selector switches
  • Check all parameters on load.
2 - Quarterly Preventive Maintenance:

When once im a three months, the PM activity is carried out then it is called as Quarterly PM activity. A maintenance checkpoint list is followed during maintenance activity which is given below mentioned.

  • First of all repeat monthly PM checkpoints.
  • Check any hot spot in panel.
  • Check all circuit breaker load according capacity.
  • Check thimble terminal temp.
  • Check earthing value with panel it should be less than 2 ohm.
  • Check panel accessories and accessories connection.
3 - Half Yearly Preventive Maintenance:

When once im a six months, the PM activity is carried out then it is called as half yearly PM activity. A maintenance checkpoint list is followed during maintenance activity which is given below mentioned.

  • First of all repeat monthly and quarterly PM activity.
4 - Yearly Preventive maintenance:

When once im a year, the PM activity is carried out then it is called as yearly PM activity. A maintenance checkpoint list is followed during maintenance activity which is given below mentioned.

  • First of all repeat monthly and quarterly PM activity.
  • Check all busbar connection and tight properly.
  • Calibrate all measuring instruments like as ammeter and voltmeter etc.
  • all circuit breaker maintenance properly.
  • All vaccuam or SF6 circuit breaker IR value test according short circuit, earth fault , overload and instantanius fault.
  • All protection relay testing according their fault parameter setting.
  • HT panel earth resistance value check. It should be as per default value.

Go back to index ↑

Learn Fast and Improve Your Skill in Electrical Field Basic and practical theory, repair and maintenance, protection and testing.

For Support Us :-

Dear respected visitors, we kindly request your support and donations
so that we can be motivated to provide valuable content
free of charge...



For Any Query :-   info@electricaltopic.com

Subscribe for Get Latest Post Updates in Your Email Inbox
Join Free Email Service